Modelling List of what has been modelled and how the stages are to relate to the construction industry.
-Coordinate with team members on the list
-Reference back to the construction methods
-List for the HUD
Saturday, May 4, 2013
Tuesday, April 30, 2013
Week 07: Progress
Construction Update: As per the builders advice on structure and design, the construction of the roof over the curtain wall is not supported by anything. There is an overhand of rafters, beams and roof structure which has no support. I have designed a column and beam structure for the Concrete model which will be constructed out of Steel I-Beams.
One Steel - Universal Beams
AS Standard: AS/NZS 3679.1
Grade: 300PLUS, AS/NZS 3679.1-350
Size Range: 150 UB to 610 UB
Standard Length: 9.0m, 10.5m, 12.0m, 13.5m, 15.0m, 16.5m, 18.0m, 20.0m
Hot Rolled Structural Steel sections produced by OneSteel are manufactured in accordance with the requirements of Australian/New Zealand Standard AS/NZS 3679.1 Structural steel.
|
Grade: 300PLUS, AS/NZS 3679.1-350
Size Range: 150 UB to 610 UB
Standard Length: 9.0m, 10.5m, 12.0m, 13.5m, 15.0m, 16.5m, 18.0m, 20.0m
-I have modelled in Revit Architecture the support structure and designed using a standard universal beam 200UB25
-The Steel universal beam standard lengths include 9.0, 10.5, 12.0, 13.5 and 15.0. These lengths will be adequate as our length of the structure is smaller than 9.0m.
-The Steel universal column I have modelled is a 200UC46.
http://www.onesteel.com/images/db_images/promotions/steel_in_housing_3rdednp1.pdf
Design
Image 01: Initial design in Revit with Universal Beams fixed to concrete slab
Image 02: Underside view of steel structure which will support the overhanging roof design.
Image 03: An example of a 3D TImber frame model with Steel beams to support large openings
Image 04: Steel frame connection detail which includes being cut, welded and bolted. This image was a good example of the way the steel flanges and webs can be connected.
Image 05: Steel Stengths as per there shape. The I-Beams being the most supportive of large structures.
Image 06: Another example of a Timber frame building with a steel support structure over a large opening.
The connections between the steel beams and columns which they will be attached to the flange or web and connected by either being welded or bolted.
-For our design we will weld the columns to the beams with no need for additional fixings or bolts.
01
02
03
References:
http://yuanboit.en.made-in-china.com/productimage/TboxAqVMhwkn-2f0j00BZwagmbthQoU/China-Steel-Beam-Connection-for-Workshop.html
http://www.cadsoft-consult.com/blogs/architecture/2009/12/take-advantage-of-extensions-for-revit-structure-2010/
http://blog.lamidesign.com/2006/03/6030-house-floor-beam-day.html
http://housedamagephotos.blogspot.com.au/2011/03/steel-beam-header.html
http://forum.homeone.com.au/viewtopic.php?f=31&t=49878&start=10
Week 08: Intellectual Property Presentation
Presentations
There were two groups to present Intellectual Property Presentations this week. The presentations were extremely helpful for me as I am not familiar with IP and why it is important.
Interactive Architecture
Clear Presentation using Prezi. Nice use of images to clearly explain the issues and processes involved with IP. There was a lot of information as well, a lot of background knowledge of IP in the industry. I have added some points i learnt from the presentation which i did not know before. There was also great use of referencing
Geriambiance
The presentation was clearly stating IP within their project. The written presentation was clear but the design was not completly engaging as it was used in PowerPoint.
IP
- It is a legal concept which refers to the creations of the mind for which exclusive rights are recognised.
- The law gives the creator the exclusive rights
- IP can be bought, sold or licensed
-It distinguishes products or services from competitors.
- Prevents others from copying
- Most businesses have some form of IP that they need to protect
Types of IP
Patents
exp.
-If you have developed a device, method or process which is new and useful, a patent can protect it.
-Does not include creations, models, plans, schemes
-It is legally enforceable and has exclusive rights
- 2 types of patents
Standard (20 years)
Innovation (8 years)
-72 month process
Trade marks
exp. Cadbury Chocolate - Purple
- protect name,logo. packaging, shape, colour, sound
- registered/un-registered
- 15 month process
Registered Designs
exp. apple smart cover
-protect the appearance of a design
-Term 10 years
-needs to be need and distinctive
Copyright
exp. Architectural drawings/ deisgn
-artistic, music, dramatic and literary works
-term life of author plus 70 years
There were two groups to present Intellectual Property Presentations this week. The presentations were extremely helpful for me as I am not familiar with IP and why it is important.
Interactive Architecture
Clear Presentation using Prezi. Nice use of images to clearly explain the issues and processes involved with IP. There was a lot of information as well, a lot of background knowledge of IP in the industry. I have added some points i learnt from the presentation which i did not know before. There was also great use of referencing
Geriambiance
The presentation was clearly stating IP within their project. The written presentation was clear but the design was not completly engaging as it was used in PowerPoint.
IP
- It is a legal concept which refers to the creations of the mind for which exclusive rights are recognised.
- The law gives the creator the exclusive rights
- IP can be bought, sold or licensed
-It distinguishes products or services from competitors.
- Prevents others from copying
- Most businesses have some form of IP that they need to protect
Types of IP
Patents
exp.
-If you have developed a device, method or process which is new and useful, a patent can protect it.
-Does not include creations, models, plans, schemes
-It is legally enforceable and has exclusive rights
- 2 types of patents
Standard (20 years)
Innovation (8 years)
-72 month process
Trade marks
exp. Cadbury Chocolate - Purple
- protect name,logo. packaging, shape, colour, sound
- registered/un-registered
- 15 month process
Registered Designs
exp. apple smart cover
-protect the appearance of a design
-Term 10 years
-needs to be need and distinctive
Copyright
exp. Architectural drawings/ deisgn
-artistic, music, dramatic and literary works
-term life of author plus 70 years
Week 07: Communication Presentation
Communication presentation - Shades of Black
The simple prezi layout is effective with minimal text, large headings and interesting images. Communication is a major element of any project and needs to be organised accordingly.
The presentation was broken down into categories which included:
Methods - Strategies, Structure
Platforms
Responsibilities - Personal Roles
Integrity/Performance - measurements, project communication performance
Longevity - Relevance, Aims, Targeting Audience
There presentation gave a brief explanation to the sub-category in relation to the larger picture and then is referenced back to their project and how that has helped them through the stages of the assignment. This idea was the main concept in our presentation as well to breifly explain what we were talking about then linking back to the project we are working on.
The simple prezi layout is effective with minimal text, large headings and interesting images. Communication is a major element of any project and needs to be organised accordingly.
The presentation was broken down into categories which included:
Methods - Strategies, Structure
Platforms
Responsibilities - Personal Roles
Integrity/Performance - measurements, project communication performance
Longevity - Relevance, Aims, Targeting Audience
There presentation gave a brief explanation to the sub-category in relation to the larger picture and then is referenced back to their project and how that has helped them through the stages of the assignment. This idea was the main concept in our presentation as well to breifly explain what we were talking about then linking back to the project we are working on.
Monday, April 15, 2013
Week 06: Planning Presentation
Aim of the Project
The aim of the project is a mixture of the reasons for undertaking the
assignment as well as the opportunities that will evolve from it. The aims and
objectives need to be analysed in the initial stages of the works to deliver a successful
project. This planning section will develop the schematic design, ideas and
collaborations to develop the project brief.
Our Project
Outline
Project 'Situation Engine' is a visual expose,
informative and communication tool that will enable clients, industry and trade
professionals a perspective view in analysing stages of construction in a real
time environment using CryEngine3.
The project will produce two 3D models, recreated
from the Revit Architecture Sample model that will comply with the Australian
Standards and the National Construction Code. They will be showcased using the
CryEngine3 program in real time displaying a live construction site. The
project will emphasize different construction methods, various construction
stages, different materials, tools and equipment that would likely be used on
our assumed site in Sydney.
The overall result will allow clients to better understand and
experience the stages within the engine, and allow trades professionals to
manage construction phases, effectively reducing cost, time, and waste
management. Additionally, it can be used as training environments for new or
existing tradespeople entering the field.
Outputs
The outputs
of a project need strategic planning and design outcomes to define the tasks
and breakdown structure of the assignment. The ideas and implementation need to
be clearly defined to complete the initial stages of planning any project. These
outputs will determine project objectives, opportunities, risks and
constraints. Once the outputs of a project are determined the collaboration of
the team will establish project roles, structure, time frames and the individual
and group milestones that need to be achieved.
Our Project Outputs
The project will
engage the emerging technologies in an innovative way to inform people involved
within the built environment. The
project will produce a real time construction site in a virtual environment
placed in the CryEngine3. The initial planning of the assignment involved defining
roles and structure of the team members.
The
establishment of the assignment was to create ‘a real life project’, to be
built in the Eastern Suburbs of Sydney. The architectural planning based
assessments include the ‘assumed’ site,
local planning and development controls combined with the recreated Revit
Architecture sample models. Further research into the local authority and their
planning instruments helped determine the design of the building and if they
were to comply with the governing body. The construction of the models was
researched and analysed using the Building codes and standards, feedback from
Builders in Sydney and researching construction reports and precedents in the
industry. These stages have been
completed and the next stages of the assignment have been planned and the roles
and structure established.
The models designed
through Building Information Modelling (BIM) will be placed into CryEngine3.
The model will be separated into stages and construction details and methods
displayed. The final interactive environment will explore how building designs
can be displayed using the emerging technologies as an informative tool.
Sunday, April 14, 2013
Detailed Crysis Stages
Stage 01:
GROUND WORKS AND SUB-FLOOR
For Both models:
5. Place concrete into Crysis for the footings
Next...
01. Revit Sample Model:
02. Timber Model
GROUND WORKS AND SUB-FLOOR
For Both models:
- First Site placed in Crysis (uncleared) - vegetation including trees, rocks, shrubs, existing slope and typography.
- Second Site placed in Crysis (cleared and excavated) - vegetation disappears excavation of the site to the level of (underside of concrete slab), Site fences erected
- Third Site in Crysis (excavation) - excavation of strip and pad footings
- Prepare Footings for Concrete fill
- Construct form-work
- Waterproof membrane (plastic sheeting)
- Reinforcement Supports (Chairs)
- Reinforcement (Bars and cages made up for strip and pad footings)
5. Place concrete into Crysis for the footings
Next...
01. Revit Sample Model:
- Preparation for Concrete slab on Ground
- Pipework for the dwelling (placed under kitchen, laundry and bathrooms)
- Vapour Barrier (Plastic sheeting)
- Reinforcement Supports (Chairs)
- Reinforcement (Bars and cages made up for strip and pad footings)
02. Timber Model
- Fix Timber Post Anchors to Pad footings
- Fix Timber Posts
- Fix bearers to Timber Post grid, as per detail
- Fix Floor Joists
Tuesday, April 9, 2013
Site stages for Crysis
Acceptable Standards of Domestic Construction
1. Site Preparation
- Sediment control
ensure that sedimentation and erosion control measures are in place and maintained as required by the local authority. (Sediment fences, divert uncontaminated water away from site, prevent contaminated water from leaving the site
http://www.yourhome.gov.au/technical/fs28.html
- Setup Site facilities
Contractors have to provide welfare facilities including Site toilets, access to water and allocated rest area as well as a site office, site materials storage, access routes, deliveries area, waste management, appropriate signage and fencing as needed
- Clearing the site
Clear vegetation and organic matter from the area of the building, clear approved trees to be removed, tree roots and stumps from 2 metres around the extent of the building. Retain topsoil for later use. Protect existing trees by fencing them off to prevent filling or excavation of the root system.
2. Sub Floor Structure
- Foundations
The footing designs are to comply with the Australian Standard AS2870 and to be certified by a structural engineer.
- Excavation and Filling
Excavate trenches for footings to an even-bearing capacity.
- Site Drainage
Provide subsoil drains to the higher side of excavation in sloping site excavtions. Build drains with falls to storm-water lines to a min of 1:100 fall.
-General
- Order Steel Reinforcements, waterproof membrane, reinforcement supports, sand and fill for appropriate footing design.
- Construct Steel Reinforcement 'cages' on site and place into footings
- Fill with Concrete
1. Site Preparation
- Sediment control
ensure that sedimentation and erosion control measures are in place and maintained as required by the local authority. (Sediment fences, divert uncontaminated water away from site, prevent contaminated water from leaving the site
http://www.yourhome.gov.au/technical/fs28.html
- Setup Site facilities
Contractors have to provide welfare facilities including Site toilets, access to water and allocated rest area as well as a site office, site materials storage, access routes, deliveries area, waste management, appropriate signage and fencing as needed
- Clearing the site
Clear vegetation and organic matter from the area of the building, clear approved trees to be removed, tree roots and stumps from 2 metres around the extent of the building. Retain topsoil for later use. Protect existing trees by fencing them off to prevent filling or excavation of the root system.
2. Sub Floor Structure
- Foundations
The footing designs are to comply with the Australian Standard AS2870 and to be certified by a structural engineer.
- Excavation and Filling
Excavate trenches for footings to an even-bearing capacity.
- Site Drainage
Provide subsoil drains to the higher side of excavation in sloping site excavtions. Build drains with falls to storm-water lines to a min of 1:100 fall.
-General
- Order Steel Reinforcements, waterproof membrane, reinforcement supports, sand and fill for appropriate footing design.
- Construct Steel Reinforcement 'cages' on site and place into footings
- Fill with Concrete