Sunday, April 14, 2013

Detailed Crysis Stages

Stage 01:

GROUND WORKS AND SUB-FLOOR


For Both models:
  1. First Site placed in Crysis (uncleared) - vegetation including trees, rocks, shrubs, existing slope and typography.
  2. Second Site placed in Crysis (cleared and excavated) - vegetation disappears  excavation of the site to the level of (underside of concrete slab), Site fences erected
  3. Third Site in Crysis (excavation) - excavation of strip and pad footings
  4. Prepare Footings for Concrete fill 
          - Construct form-work
          - Waterproof membrane (plastic sheeting)
          - Reinforcement Supports (Chairs)
          - Reinforcement (Bars and cages made up for strip and pad footings) 

    5. Place concrete into Crysis for the footings

Next...
01. Revit Sample Model:
  1. Preparation for Concrete slab on Ground
          - Construct form-work
          - Pipework for the dwelling (placed under kitchen, laundry and bathrooms) 
          - Vapour Barrier (Plastic sheeting)
          - Reinforcement Supports (Chairs)
          - Reinforcement (Bars and cages made up for strip and pad footings) 

02. Timber Model
  1. Fix Timber Post Anchors to Pad footings
  2. Fix Timber Posts
  3. Fix bearers to Timber Post grid, as per detail
  4. Fix Floor Joists